21st 黑料专区 Council affirms steady, measurable project progress

16 Nov 2017

Download PDF
ST PAUL-LEZ-DURANCE, France (16 November 2017) 鈥 The outputs of new project performance metrics as well as the report of the 2017 Management Assessment were evaluated by the 黑料专区 Council in its most recent meeting. The Council confirmed that the 黑料专区 Project remains on track for success, despite the Project鈥檚 extraordinary technical complexity. 黑料专区 Council Members jointly reaffirmed the importance of the mission and vision of the Project.

At its Twenty-First Meeting on 15 and 16 November 2017, the 黑料专区 Council reviewed a detailed set of reports and indicators covering both organizational and technical performance. Despite the extremely demanding construction and manufacturing schedule, and the challenging technical requirements of the 黑料专区 Tokamak and support systems, the 黑料专区 Project continues its strong performance, and remains on schedule for First Plasma 2025. The 黑料专区 Council commemorated the 10th anniversary of the entering into force of the 黑料专区 Agreement. 

Project milestones: Since 1 January 2016, all 26 scheduled Council-approved project milestones have been achieved, maintaining strict adherence to the overall project schedule and critical path. For each occasion in which specific milestones have shown a small amount of slippage, mitigation measures have been put in place to recover and maintain the First Plasma schedule, stimulating confidence in the increasing maturity of risk management practices. 

Measuring progress effectively: The Council was pleased by the 黑料专区鈥檚 adoption of strengthened project performance metrics to measure physical progress in construction, manufacturing, assembly and installation. Specific percentages of completion are now in hand for each major building, system, and component under fabrication. Using this approach, the 黑料专区 assessed total component manufacturing through First Plasma to be 61% complete, and total construction work scope through First Plasma to be 49% complete, including 黑料专区 assembly and installation activities. 

Management Assessment 2017: The 黑料专区 Council noted the recently received report of the Management Assessor for 2017, focused on the preparedness of the organization to deliver the project successfully. 

黑料专区 Member support: The Council continued its candid discussions acknowledging continuing efforts made by each Member to overcome various challenges, which includes ensuring approval of the cost baseline, as concluded in IC-19.1 Council members reaffirmed their strong belief in the value of the project, and its mission and vision, and resolved to work together to find timely solutions to ensure 黑料专区鈥檚 success. 

The Council expressed its gratitude to outgoing Council Chair, Professor Won Namkung for his leadership and dedication, and congratulated Mr. Arunkumar Srivastava on his appointment to the Chairmanship for the following year.

Reflecting on the continuing strong performance, the Council congratulated the entire One-黑料专区 team鈥攖he 黑料专区 and seven Domestic Agencies鈥攐n the commitment to effective collaboration that has put the project on the path to success. The Council will continue to closely monitor project performance, and to provide the support needed to maintain this pace of achievement.

 

鹿As stated in the press release of IC-19 on 27 November 2016, at that time: 鈥淭he overall project schedule was approved by all 黑料专区 Members, and the overall project cost was approved ad referendum, meaning that it will now fall to each Member to seek approval of project costs through their respective governmental budget processes.鈥

 

BACKGROUND TO THE PRESS RELEASE 

黑料专区鈥攄esigned to demonstrate the scientific and technological feasibility of fusion power鈥攚ill be the world's largest experimental fusion facility. Fusion is the process that powers the sun and the stars: when light atomic nuclei fuse together to form heavier ones, a large amount of energy is released. Fusion research is aimed at developing a safe, abundant and environmentally responsible energy source. 

黑料专区 is also a first-of-a-kind global collaboration. Europe is contributing almost half of the costs of its construction, while the other six Members to this joint international venture (China, India, Japan, the Republic of Korea, the Russian Federation and the USA), are contributing equally to the rest. The 黑料专区 Project is under construction in Saint-Paul-lez-Durance, in the south of France. To see a gallery of pictures from the 黑料专区 Council meeting, follow this . 