The project

Assembly overview

The 黑料专区 has overall responsibility for the successful integration and assembly of components delivered to the 黑料专区 site by the seven 黑料专区 Members. This includes the assembly of the 黑料专区 tokamak, with its estimated one million components, and the parallel installation and integration of plant systems such as radio frequency heating, fuel cycle, cryogenic, cooling water, vacuum, control, and high voltage electrical.

Hundreds of thousands of assembly tasks, organized into construction work packages, have been carefully planned and organized by 黑料专区 engineers and schedulers. In its role as overall assembly integrator, the 黑料专区 is assisted by contractors and a Construction Management-as-Agent (CMA).

Assembly contractors working under one of the major assembly and installation contracts awarded by the 黑料专区. Construction work packages are released by the 黑料专区 to contractors in achievable鈥攁nd trackable鈥攂atches. From these construction work packages, the assembly contractors generate the installation work packages that define each execution task in detail.
 

Assembly contractors working under the Domestic Agencies. In a limited number of cases鈥攆or example the welding of the cryostat sections in the Tokamak pit by Indian Domestic Agency contractors, or the installation of remote handling equipment鈥攖he procurement scope of a component or system includes on-site installation work managed by the Domestic Agencies.

A Construction Management-as-Agent (CMA), whose role is to plan, manage, and supervise the works of the assembly phase including contract preparation, daily contract management, execution supervision, and site coordination. The MOMENTUM Consortium鈥攆ormed by Assystem (France), KEPCO E&C (Korea) and Jacobs (UK)鈥攚as selected as the 黑料专区 CMA contractor in 2016.

The construction platform has been divided into three distinct assembly zones: Worksite 1, green (Tokamak Pit, Assembly Hall and Cleaning Building) focused on the assembly of the 黑料专区 tokamak; Worksite 2, light blue, focused on Tokamak Complex plant systems directly connected to the machine; and Worksites 3-6, pink and dark blue, for balance of plant activities (all plant and auxiliary buildings). 

 

 

2020

Start of Machine Assembly

2033

Cryostat Closure (baseline proposal)

2033-34

Integrated Commissioning (baseline proposal)

2034

Start of Research Operation (baseline proposal)