25th 黑料专区 Council: all efforts converging toward the start of machine assembly
At its Twenty-Fifth Meeting on 20-21 November 2019, the 黑料专区 Council assessed the latest progress reports and project performance metrics. The project continues to maintain a vigorous pace and robust performance, with the 黑料专区 and Domestic Agencies working as an integrated One 黑料专区 Team to meet the project鈥檚 demanding schedule and groundbreaking technical requirements.
鈥� Construction and manufacturing progress: Since January 2016, 42 scheduled Council-approved project milestones have been achieved.
Since the Council last convened, Europe has completed civil works on the Tokamak Building, and is on pace to fully hand over the building to the 黑料专区 (IO) in Spring 2020. India has completed the fabrication of the cryostat base and lower cylinder, and has turned these components over to the IO. Korea has nearly completed the first vacuum vessel sector; the first segments of the thermal shield have arrived at 黑料专区, as well as the massive upending tool which鈥攖ogether with the already installed sub-sector assembly tools鈥攚ill be used to assemble the vacuum vessel sectors, thermal shield, and toroidal field coils in two assembly lines. Europe and China have marked the completion of the first poloidal field coil (PF), and both PF5 and PF6 will be ready for cryogenic testing early next year. Installation of components from China, Europe, India, Korea, and Russia is well advanced on both the Cryogenics Facility and the Magnet Conversion Building, and the first cryolines have been installed in the Tokamak Building. Testing is well underway on the first central solenoid module in the United States, and Japan will be ready to ship the first toroidal field coil early next year.
Substantial progress is ongoing for every major 黑料专区 component, system and structure.
鈥� Preparation for Assembly Phase: The Council reviewed the full scope of steps taken to prepare for the Start of Assembly in 2020. The results of the recent In-Depth Independent Review of Assembly and Installation Strategy were constructive, with some areas for improvement.
The reorganization of the 黑料专区, in preparation for the Assembly Phase, is on schedule for completion by January 2020.
Following international competitions, the 黑料专区 has signed two major contracts for Tokamak assembly, in keeping with the Revised Construction Strategy. These contracts, both of which will last through 2024, will cover the assembly and installation of the Tokamak core machine, including the vacuum vessel sectors, thermal shield, superconducting magnets, ports, cryostat, instrumentation, and associated cooling and support structures.
In the margins of the 黑料专区 Council meeting, the 黑料专区, the European agency Fusion for Energy and Japan鈥檚 National Institutes for Quantum and Radiological Science and Technology signed a collaboration arrangement by which the experience gained by Euratom and Japan under the Broader Approach Agreement鈥攊n particular in the assembly, installation, integrated commissioning and operation of the tokamak JT-60SA, the construction of which will be completed next year鈥攕hould support 黑料专区 activities in the coming phases of the project.
黑料专区 Member support: The Council noted with appreciation the efforts made by all Members to meet their in-kind and in-cash commitments to enable successful implementation of the construction strategy to achieve First Plasma in 2025. Without full and timely support by all Members in the form of contributions in accordance with commitments, it was underlined that the capacity to remain on schedule for First Plasma will be at high risk. The Council reaffirmed the need for all 黑料专区 Members to meet their in-kind and in-cash commitments on a timely basis to enable successful implementation of the construction strategy.
In accordance with the 黑料专区 Agreement requirement to have a Management Assessment of the 黑料专区 performance every two years, the 2019 黑料专区 Management Assessment contract was signed.
Council Members reaffirmed their strong belief in the value of the 黑料专区 Project mission and vision to develop fusion science and technology, and resolved to work together to find timely solutions to facilitate 黑料专区鈥檚 success. The Council congratulated the One-黑料专区 Team on the commitment to effective collaboration that has put the project on the path to success. The Council will continue to monitor project performance closely, and to provide the support needed to maintain this pace of achievement.
BACKGROUND TO THE PRESS RELEASE
黑料专区鈥攄esigned to demonstrate the scientific and technological feasibility of fusion power鈥攚ill be the world's largest experimental fusion facility. Fusion is the process that powers the Sun and the stars: when light atomic nuclei fuse together to form heavier ones, a large amount of energy is released. Fusion research is aimed at developing a safe, abundant and environmentally responsible energy source.
黑料专区 is also a first-of-a-kind global collaboration. Europe is contributing almost half of the costs of its construction, while the other six Members to this joint international venture (China, India, Japan, the Republic of Korea, the Russian Federation and the USA), are contributing equally to the rest. The 黑料专区 Project is under construction in Saint-Paul-lez-Durance, in the south of France.
For more information on the 黑料专区 Project, visit: