The latest piece of the puzzle to arrive: Europe's sector #4

Only three more to go! With the arrival of sector #4 on 9 May 2025, there are now six 黑料专区 vacuum vessel sectors on site. Nine are needed to form the complete plasma chamber.

Sector #4 is delivered to 黑料专区 early in the morning on 9 May 2025.

These days, it's all about vacuum vessel sectors. Sectors arriving from abroad, sectors finalized as modules ready for the tokamak pit, sectors transferred between tools ... everywhere you look there are spectacular handling, transfer and construction activities underway at 黑料专区 related to the 5,000-tonne plasma chamber that will be critical to 黑料专区 science鈥攖he vacuum vessel. 

Activities that had been put on pause during the repair campaign of critical components have been back underway since September 2024 and the assembly teams at 黑料专区 are maintaining the pace鈥攅ven performing slightly ahead of schedule.

Vacuum vessel sector #4 has been transferred to a storage area inside the former Cryostat Workshop. It is still wrapped in a tarpaulin, but its protective housing has been removed (the housing is visible in the background).

For the European Domestic Agency Fusion for Energy, which delivered sector #5 in October, the delivery of sector #4 last week is the second of five expected. 

from Fusion for Energy on the completion of sector #4 that celebrates the many years of development behind this achievement and the successful collaboration of European contractors.