The year in pictures

In 2015, 黑料专区 looked to its past and celebrated three important events in its history: the 30th anniversary of the Reagan-Gorbachev summit meeting in Geneva, in November 1985, when the decision was taken to launch "the widest practical international cooperation" on fusion energy; the 10th anniversary of the unanimous vote in June 2005 in favour of the European site for 黑料专区 in Saint-Paul-lez-Durance, France; and the 5th anniversary of the beginning of construction on the 黑料专区 site.

In 2015, 黑料专区 also looked to its future by establishing a new way of working, based on a more efficient integration of all the project players鈥攖he 黑料专区 Central Team, the seven Domestic Agencies, laboratories and institutions鈥攗nder the stewardship of the new Director-General of the 黑料专区, Bernard Bigot, who took up the reins of the project in March. Eight months of hard work produced the detailed schedule that was submitted to the 黑料专区 Council in November鈥攖he ultimate Baseline that will lead to First Plasma.

Visible from afar, a spectacular feature was added to the 黑料专区 worksite: the steel structure of the Assembly Hall, soon to be clad with mirror-like stainless steel, now stands as a landmark in the Durance River valley.

Below ground level work on the Tokamak Complex progressed steadily throughout the year. Thick walls and sturdy columns have risen at the lowest basement level (B2) and working is starting on the next floor (B1).

In workshops and factories throughout the world, the 黑料专区 Members are engaged in manufacturing machine components and plant systems. A steady flow of deliveries is now reaching the 黑料专区 site.

The first Highly Exceptional Load reached 黑料专区 in January 2015, in the shape a 90-tonne electrical transformer procured by the US. Twelve months later, the first actual machine components鈥攕egments of the 黑料专区 cryostat procured by India鈥攖ravelled the 黑料专区 Itinerary and are now waiting in the Cryostat Workshop to be welded together.

Thirty years after its inception and five since construction began in earnest, the 黑料专区 Project has acquired a tangible and spectacular reality. The "paper project" has turned into an industrial venture that strongly interacts with its economic environment; to this day, more than EUR 7 billion in contracts are ongoing in both construction and manufacturing.